| astronautix.com | Apollo CSM |
![]() |
| Apollo 15 CSM - Apollo 15 CSM over Lunar Surface Credit: NASA. 19,085 bytes. 199 x 401 pixels. |
The Apollo Command Service Module was the spacecraft developed by NASA for earth and lunar orbit missions. Block I command service modules, which lacked forward docking tunnels and hatches, never flew manned after the Apollo 204 fire killed its crew on the pad. Block II CSM's successfully ferried crews to the moon, to the Skylab space station, and to a joint docking with the Russian Soyuz. The Apollo was abandoned in favor of the shuttle to continue American manned spaceflight.
Unit Price $ : 77.00 million. Craft.Crew Size: 3. Total Length: 11.0 m. Maximum Diameter: 3.9 m. Total Habitable Volume: 6.17 m3. Total Mass: 30,329 kg. Total Propellants: 18,488 kg. Total RCS Impulse: 384,860.00 kgf-sec. Primary Engine Thrust: 9,979 kgf. Main Engine Propellants: N2O4/UDMH. Main Engine Isp: 314 sec. Total spacecraft delta v: 2,804 m/s. Electric system: 6.30 total average kW. Electric System: 690.00 total kWh. Electrical System: Fuel Cells.
The Rocket and Satellite Research Panel, established in 1946 as the V-2 Upper Atmosphere Research Panel and renamed the Upper Atmosphere Rocket Research Panel in 1948, together with the American Rocket Society proposed a national space flight program and a unified National Space Establishment. The mission of such an Establishment would be nonmilitary in nature, specifically excluding space weapons development and military operations in space. By 1959, this Establishment should have achieved an unmanned instrumented hard lunar landing and, by 1960, an unmanned instrumented lunar satellite and soft lunar landing. Manned circumnavigation of the moon with return to earth should have been accomplished by 1965 with a manned lunar landing mission taking place by 1968. Beginning in 1970, a permanent lunar base should be possible.
NACA established a Special Committee on Space Technology to study the problems of space flight. H. Guyford Stever of the Massachusetts Institute of Technology (MIT) was named Chairman. On November 21, 1957, NACA had authorized formation of the Committee.
The Stever Committee, which had been set up on January 12, submitted its report on the civilian space program to NASA. Among the recommendations:
A Working Group on Lunar Exploration was established by NASA at a meeting at Jet Propulsion Laboratory (JPL). Members of NASA, JPL, Army Ballistic Missile Agency, California Institute of Technology, and the University of California participated in the meeting. The Working Group was assigned the responsibility of preparing a lunar exploration program, which was outlined: circumlunar vehicles, unmanned and manned; hard lunar impact; close lunar satellites; soft lunar landings (instrumented). Preliminary studies showed that the Saturn booster with an intercontinental ballistic missile as a second stage and a Centaur as a third stage, would be capable of launching manned lunar circumnavigation spacecraft and instrumented packages of about one ton to a soft landing on the moon.
Roy W. Johnson, Director of the Advanced Research Projects Agency (ARPA), testified before the House Committee on Science and Astronautics that DOD and ARPA had no lunar landing program. Herbert F. York, DOD Director of Defense Research and Engineering, testified that exploration of the moon was a NASA responsibility.
At the second meeting of the Research Steering Committee on Manned Space Flight, held at the Ames Research Center, members presented reports on intermediate steps toward a manned lunar landing and return.
Bruce T. Lundin of the Lewis Research Center reported to members on propulsion requirements for various modes of manned lunar landing missions, assuming a 10,000-pound spacecraft to be returned to earth. Lewis mission studies had shown that a launch into lunar orbit would require less energy than a direct approach and would be more desirable for guidance, landing reliability, etc. From a 500,000 foot orbit around the moon, the spacecraft would descend in free fall, applying a constant-thrust decelerating impulse at the last moment before landing. Research would be needed to develop the variable-thrust rocket engine to be used in the descent. With the use of liquid hydrogen, the launch weight of the lunar rocket and spacecraft would be 10 to 11 million pounds. Additional Details: Steps toward a manned lunar landing.
The STG New Projects Panel (proposed by H. Kurt Strass in June) held its first meeting to discuss NASA's future manned space program. Present were Strass, Chairman, Alan B. Kehlet, William S. Augerson, Jack Funk, and other STG members. Strass summarized the philosophy behind NASA's proposed objective of a manned lunar landing : maximum utilization of existing technology in a series of carefully chosen projects, each of which would provide a firm basis for the next step and be a significant advance in its own right. Additional Details: NASA's future manned space program.
At its second meeting, STG's New Projects Panel decided that the first major project to be investigated would be the second-generation reentry capsule. The Panel was presented a chart outlining the proposed sequence of events for manned lunar mission system analysis. The target date for a manned lunar landing was 1970.
A House Committee Staff Report stated that lunar flights would originate from space platforms in earth orbit according to current planning. The final decision on the method to be used, "which must be made soon," would take into consideration the difficulty of space rendezvous between a space platform and space vehicles as compared with the difficulty of developing single vehicles large enough to proceed directly from the earth to the moon.
A study of the guidance and control design for a variety of space missions began at the MIT Instrumentation Laboratory under a NASA contract.
At the third meeting of STG's New Projects Panel, Alan B. Kehlet presented suggestions for the multimanned reentry capsule. A lenticular-shaped vehicle was proposed, to ferry three occupants safely to earth from a lunar mission at a velocity of about 36,000 feet per second.
In testimony before the House Committee on Science and Astronautics, Richard E. Horner, Associate Administrator of NASA, presented NASA's ten-year plan for 1960-1970. The essential elements had been recommended by the Research Steering Committee on Manned Space Flight. NASA's Office of Program Planning and Evaluation, headed by Homer J. Stewart, formalized the ten-year plan.
On February 19, NASA officials again presented the ten-year timetable to the House Committee. A lunar soft landing with a mobile vehicle had been added for 1965. On March 28, NASA Administrator T. Keith Glennan described the plan to the Senate Committee on Aeronautical and Space Sciences. He estimated the cost of the program to be more than $1 billion in Fiscal Year 1962 and at least $1.5 billion annually over the next five years, for a total cost of $12 to $15 billion. Additional Details: NASA's Ten-Year Plan presented to Congress.
At a luncheon in Washington, Abe Silverstein, Director of the Office of Space Flight Programs, suggested the name "Apollo" for the manned space flight program that was to follow Mercury. Others at the luncheon were Don R. Ostrander from NASA Headquarters and Robert R. Gilruth, Maxime A. Faget, and Charles J. Donlan from STG.
At a NASA staff conference at Monterey, Calif., officials discussed the advanced manned space flight program, the elements of which had been presented to Congress in January. The Goddard Space Flight Center was asked to define the basic assumptions to be used by all groups in the continuing study of the lunar mission. Some problems already raised were: the type of heatshield needed for reentry and tests required to qualify it, the kind of research and development firings, and conditions that would be encountered in cislunar flight. Additional Details: Advanced manned space flight program.
Presentation by STG members of the guidelines for an advanced manned spacecraft program to NASA Centers.
Members of STG presented the proposed advanced manned spacecraft program to Wernher von Braun and 25 of his staff at Marshall Space Flight Center. During the ensuing discussion, the merits of a completely automatic circumlunar mission were compared with those of a manually operated mission. Further discussions were scheduled.
STG members presented the proposed advanced manned spacecraft program to the Lewis Research Center staff. Work at the Center applicable to the program included: analysis and preliminary development of the onboard propulsion system, trajectory analysis, and development of small rockets for midcourse and attitude control propulsion.
STG formed the Advanced Vehicle Team, reporting directly to Robert R. Gilruth, Director of the Mercury program. The Team would conduct research and make preliminary design studies for an advanced multiman spacecraft. Additional Details: Advanced Vehicle Team to make preliminary design for advanced multiman spacecraft.
Robert O. Piland, Head of the STG Advanced Vehicle Team, and Stanley C. White of STG attended a meeting in Washington, D. C., sponsored by the NASA Office of Life Sciences Programs, to discuss radiation and its effect on manned space flight. Their research showed that it would be impracticable to shield against the inner Van Allen belt radiation but possible to shield against the outer belt with a moderate amount of protection. Additional Details: Radiation and its effect on manned space flight.
NASA Director of Space Flight Programs Abe Silverstein notified Harry J. Goett, Director of the Goddard Space Flight Center, that NASA Administrator T. Keith Glennan had approved the name "Apollo" for the advanced manned space flight program. The program would be so designated at the forthcoming NASA-Industry Program Plans Conference.
The first NASA-Industry Program Plans Conference was held in Washington, D.C. The purpose was to give industrial management an overall picture of the NASA program and to establish a basis for subsequent conferences to be held at various NASA Centers. The current status of NASA programs was outlined, including long-range planning, launch vehicles, structures and materials research, manned space flight, and life sciences.
NASA Deputy Administrator Hugh L. Dryden announced that the advanced manned space flight program had been named "Apollo." George M. Low, NASA Chief of Manned Space Flight, stated that circumlunar flight and earth orbit missions would be carried out before 1970. This program would lead eventually to a manned lunar landing and a permanent manned space station. Additional Details: Announcement of the Apollo program to American industry.
![]() | Apollo CSM Credit: © Mark Wade. 3,260 bytes. 341 x 174 pixels. |
The Goddard Space Flight Center GSFC conducted its industry conference in Washington, D.C., presenting details of GSFC projects, current and future. The objectives of the proposed six-month feasibility contracts for an advanced manned spacecraft were announced. Additional Details: Industry briefing on feasibility studies for the Apollo spacecraft.
An STG briefing was held at Langley Field, Va., for prospective bidders on three six-month feasibility studies of an advanced manned spacecraft as part of the Apollo program. A formal Request for Proposal was issued at the conference.
Charles J. Donlan of STG, Chairman of the Evaluation Board which would consider contractors' proposals on feasibility studies for an advanced manned spacecraft, invited the Directors of Ames Research Center, Jet Propulsion Laboratory, Flight Research Center, Lewis Research Center, Langley Research Center, and Marshall Space Flight Center to name representatives to the Evaluation Board. The first meeting was to be held on October 10 at Langley Field, Va.
Contractors' proposals on feasibility studies for an advanced manned spacecraft were received by STG. Sixty-four companies expressed interest in the Apollo program, and of these 14 actually submitted proposals: The Boeing Airplane Company; Chance Vought Corporation; Convair/Astronautics Division of General Dynamics Corporation; Cornell Aeronautical Laboratory, Inc.; Douglas Aircraft Company; General Electric Company; Goodyear Aircraft Corporation; Grumman Aircraft Engineering Corporation; Guardite Division of American Marietta Company; Lockheed Aircraft Corporation; The Martin Company; North American Aviation, Inc.; and Republic Aviation Corporation. These 14 companies, later reduced to 12 when Cornell and Guardite withdrew, were subsequently invited to submit prime contractor proposals for the Apollo spacecraft development in 1961. The Technical Assessment Panels began evaluation of contractors' proposals on October 10.
The Technical Assessment Panels presented to the Evaluation Board their findings on the contractors' proposals for feasibility studies of an advanced manned spacecraft. On October 24, the Evaluation Board findings and recommendations were presented to the STG Director.
From 16 bids, Convair, General Electric, and Martin selected to conduct $250,000 study contracts. Meanwhile Space Task Group Langley undertakes its own studies, settling on Apollo CM configuration as actually built by October 1960.
A joint briefing on the Apollo and Saturn programs was held at Marshall Space Flight Center MSFC, attended by representatives of STG and MSFC. Maxime A. Faget of STG and MSFC Director Wernher von Braun agreed that a joint STG-MSFC program would be developed to accomplish a manned lunar landing. Areas of responsibility were: MSFC launch vehicle and landing on the moon; STG - lunar orbit, landing, and return to earth.
The first technical review of the General Electric Company Apollo feasibility study was held at the contractor's Missile and Space Vehicle Department. Company representatives presented reports on the study so that STG representatives might review progress, provide General Electric with pertinent information from NASA or other sources, and discuss and advise as to the course of the study.
The Martin Company presented the first technical review of its Apollo feasibility study to STG officials in Baltimore, Md. At the suggestion of STG, Martin agreed to reorient the study in several areas: putting more emphasis on lunar orbits, putting man in the system, and considering landing and recovery in the initial design of the spacecraft.
Convair/Astronautics Division of the General Dynamics Corporation held its first technical review of the Apollo feasibility study in San Diego, Calif. Brief presentations were made by contractor and subcontractor technical specialists to STG representatives. Convair/Astronautics' first approach was oriented toward the modular concept, but STG suggested that the integral spacecraft concept should be investigated.
The MIT Instrumentation Laboratory submitted a formal proposal to NASA for a study of a navigation and guidance system for the Apollo spacecraft.
The Manned Lunar Landing Task Group (Low Committee) set up by the Space Exploration Program Council was instructed to prepare a position paper for the NASA Fiscal Year 1962 budget presentation to Congress. The paper was to be a concise statement of NASA's lunar program for Fiscal Year 1962 and was to present the lunar mission in term of both direct ascent and rendezvous. The rendezvous program would be designed to develop a manned spacecraft capability in near space, regardless of whether such a technique would be needed for manned lunar landing. In addition to answering such questions as the reason for not eliminating one of the two mission approaches, the Group was to estimate the cost of the lunar mission and the date of its accomplishment, though not in specific terms. Although the decision to land a man on the moon had not been approved, it was to be stressed that the development of the scientific and technical capability for a manned lunar landing was a prime NASA goal, though not the only one. The first meeting of the Group was to be held on January 9.
The Marshall Space Flight Center awarded contracts to the Douglas Aircraft Company and Chance Vought Corporation to study the launching of manned exploratory expeditions into lunar and interplanetary space from earth orbits.
NASA announced that the Lockheed Aircraft Corporation had been awarded a contract by the Marshall Space Flight Center to study the feasibility of refueling a spacecraft in orbit.
William W. Petynia of STG visited the Convair Astronautics Division of General Dynamics Corporation to monitor the Apollo feasibility study contract. A selection of the M-1 in preference to the lenticular configuration had been made by Convair. May 17 was set as the date for the final Convair presentation to NASA.
STG completed the first draft of "Project Apollo, Phase A, General Requirements for a Proposal for a Manned Space Vehicle and System" (Statement of Work), an early step toward the spacecraft specification. A circumlunar mission was the basis for planning.
In initial study contracts, Martin proposed vehicle similar to the Apollo configuration that would eventually fly and closest to STG concepts. GE proposed design that would lead directly to Soyuz. Convair proposed a lifting body concept. All bidders were influenced by STG mid-term review that complained that they were not paying enough attention to conical blunt-body CM as envisioned by STG.
The final reports on the feasibility study contracts for the advanced manned spacecraft were submitted to STG at Langley Field, Va., by the General Electric Company, Convair Astronautics Division of General Dynamics Corporation, and The Martin Company. These studies had begun in November 1960.
The second draft of a Statement of Work for the development of an advanced manned spacecraft was completed, incorporating results from NASA in-house and contractor feasibility studies.
The Fleming Committee, which had been appointed on May 2, submitted its report to NASA associate Administrator Robert C. Seamans, Jr., on the feasibility of a manned lunar landing program. The Committee concluded that the lunar mission could be accomplished within the decade. Chief pacing items were the first stage of the launch vehicle and the facilities for testing and launching the booster. It also concluded that information on solar flare radiation and lunar surface characteristics should be obtained as soon as possible, since these factors would influence spacecraft design. Special mention was made of the need for a strong management organization.
STG completed a detailed assessment of the results of the Project Apollo feasibility studies submitted by the three study contractors: the General Electric Company, Convair/Astronautics Division of the General Dynamics Corporation, and The Martin Company. (Their findings were reflected in the Statement of Work sent to prospective bidders on the spacecraft contract on July 28.)
1,000 persons from 300 potential Project Apollo contractors and government agencies attended the conference. STG pushed the conical CM shape, in defiance of Gilruth's preference for the competitive blunt body/lifting body designs. Scientists from NASA, the General Electric Company, The Martin Company, and General Dynamics/Astronautics presented the results of studies on Apollo requirements. Within the next four to six weeks NASA was expected to draw up the final details and specifications for the Apollo spacecraft.
NASA invited 12 companies to submit prime contractor proposals for the Apollo spacecraft by October 9: The Boeing Airplane Company, Chance Vought Corporation, Douglas Aircraft Company, General Dynamics/Convair, the General Electric Company, Goodyear Aircraft Corporation, Grumman Aircraft Engineering Corporation, Lockheed Aircraft Corporation, McDonnell Aircraft Corporation, The Martin Company, North American Aviation, Inc., and Republic Aviation Corporation. Additional Details: NASA invitation to bids for Apollo prime contract.
NASA selected MIT's Instrumentation Laboratory to develop the guidance-navigation system for Project Apollo spacecraft. This first major Apollo contract was required since guidance-navigation system is basic to overall Apollo mission. The Instrumentation Laboratory of MIT, a nonprofit organization headed by C. Stark Draper, has been involved in a variety of guidance and navigation systems developments for 20 years. This first major Apollo contract had a long lead-time, was basic to the overall Apollo mission, and would be directed by STG.
STG held a pre-proposal briefing at Langley Field, Va., to answer bidders' questions pertaining to the Request for Proposal for the development of the Apollo spacecraft. 14 companies (Boeing, Vought, Douglas, GD, Goodyear, Grumman, Lockheed, Martin, McDonnell, Radio Corp, Republic, STL) attended. The winning bidder would receive contract for CSM (but not LM, if any) and integrate spacecraft with launch vehicle.
Five Bidding Teams: GD/Avco; GE/Douglas/Grumman/STL; McDonnell/Lockheed/Hughes/Vought; Martin/North American
![]() | Apollo CSM 18,052 bytes. 245 x 480 pixels. |
Officials of STG heard oral reports from representatives of five industrial teams bidding on the contract for the Apollo spacecraft: General Dynamics/Astronautics in conjunction with the Avco Corporation; General Electric Company, Missile and Space Vehicle Department, in conjunction with Douglas Aircraft Company, Grumman Aircraft Engineering Corporation, and Space Technology Laboratories, Inc.; McDonnell Aircraft Corporation in conjunction with Lockheed Aircraft Corporation, Hughes Aircraft Company, and Chance Vought Corporation of Ling-Temco-Vought, Inc.; The Martin Company; and North American Aviation, Inc. Additional Details: Presentations by industrial teams on the Apollo spacecraft.
Bid ratings: Martin 6.9; GD 6.6; North American 6.6; GE 6.4; McDonnell 6.4
The original Apollo spacecraft Statement of Work of July 28 had been substantially expanded, including a single-engine service module propulsion system using Earth-storable, hypergolic propellants. Additional Details: Apollo spacecraft Statement of Work expanded.
Despite an announcement at Martin on 27 November that they had won the Apollo program, the decision was reversed at the highest levels of the US government. NASA announced instead that the Space and Information Systems Division of North American Aviation, Inc., had been selected to design and build the Apollo spacecraft. The official line: 'the decision by NASA Administrator James E. Webb followed a comprehensive evaluation of five industry proposals by nearly 200 scientists and engineers representing both NASA and DOD. Webb had received the Source Evaluation Board findings on November 24. Although technical evaluations were very close, NAA had been selected on the basis of experience, technical competence, and cost'. NAA would be responsible for the design and development of the command module and service module. NASA expected that a separate contract for the lunar landing system would be awarded within the next six months. The MIT Instrumentation Laboratory had previously been assigned the development of the Apollo spacecraft guidance and navigation system. Both the NAA and MIT contracts would be under the direction of MSC.
The Project Apollo Statement of Work for development of the Apollo spacecraft was completed. A draft letter based on this Statement of Work was presented to NAA for review. A prenegotiation conference on the development of the Apollo spacecraft was held at Langley Field, Va.
The Apollo Spacecraft Project Office (ASPO) was established at MSC. Charles W. Frick was selected as Manager of the new Office, to assume his duties in February. Frick had been Chief of Technical Staff for General Dynamics Convair. Robert O. Piland was appointed Deputy Manager of ASPO and would serve as Acting Manager until Frick's arrival. ASPO would be responsible for the technical direction of NAA and other industrial contractors assigned to work on the Apollo spacecraft. Additional Details: Apollo Spacecraft Project Office established.
The first Apollo engineering order was issued to fabricate mockups of the Apollo command and service modules.
NAA engineers began preliminary layouts to define the elements of the command module (CM) configuration. Additional requirements and limitations imposed on the CM included reduction in diameter, paraglider compatibility, 250 pounds of radiation protection water, redundant propellant tankage for the attitude control system, and an increase in system weight and volume. Additional Details: Preliminary layouts of the Apollo command module.
On the basis of a study by NAA, a single-engine configuration was chosen as the optimum approach for the service module propulsion subsystem. The results of the study were presented to MSC representatives and NAA was authorized to issue a work statement to begin procurement of an engine for this configuration. Agreement was also reached at this meeting on a vacuum thrust level of 20,000 pounds for the engine. This would maintain a thrust-to-weight ratio of 0.4 and allow a considerable increase in the lunar liftoff weight of the spacecraft.
NASA announced that the General Electric Company had been selected for a major supporting role in the Apollo project, to provide integration analysis of the total space vehicle (including booster-spacecraft interface), ensure reliability of the entire space vehicle, and develop and operate a checkout system.
A contract for the escape rocket of the Apollo spacecraft launch escape system was awarded to the Lockheed Propulsion Company by NAA. The initial requirements were for a 200,000-pound-thrust solid- propellant rocket motor with an active thrust-vector-control subsystem. Additional Details: Contract for Apollo launch escape system rocket.
The Marquardt Corporation was selected by NAA's Space and Information Systems Division to design and build the reaction control rocket engines for the Apollo spacecraft. The contract was signed during April.
The Aerojet-General Corporation was named by NAA as a subcontractor for the Apollo service module propulsion system.
NAA awarded a development contract for the Apollo spacecraft fuel cell to Pratt & Whitney Aircraft Division of United Aircraft Corporation.
NAA was directed by the MSC Apollo Spacecraft Project Office to begin a study to define the configuration and design criteria of the service module which would make the lunar landing maneuver and touchdown.
A mockup of the Apollo command module, built by the Space and Information Systems Division of NAA, was made public for the first time during a visit to NAA by news media representatives.
The Thiokol Chemical Corporation was selected by NAA to build the solid-fuel rocket motor to be used to jettison the Apollo launch escape tower following a launch abort or during a normal mission.
President John F, Kennedy designated the Apollo program including essential spacecraft, launch vehicles, and facilities as being in the highest national priority category (DX) for research and development and for achieving operational capability.
Wernher von Braun, Director, Marshall Space Flight Center, recommended to the NASA Office of Manned Space Flight that the lunar orbit rendezvous mode be adopted for the lunar landing mission. He also recommended the development of an unmanned, fully automatic, one-way Saturn C-5 logistics vehicle in support of the lunar expedition; the acceleration of the Saturn C-1B program; the development of high-energy propulsion systems as a backup for the service module and possibly the lunar excursion module; and further development of the F-1 and J-2 engines to increase thrust or specific impulse.
Results of a preliminary investigation by NAA showed that a 100 percent oxygen atmosphere for the command module would save about 30 pounds in weight and reduce control complexity.
NASA and MIT agreed that the Instrumentation Laboratory would use the microcircuit for the prototype Apollo onboard computer. The Fairchild Controls Corporation microcircuit was the only one available in the United States.
Five NASA scientists, dressed in pressure suits, completed an exploratory study at Rocketdyne Division of the feasibility of repairing, replacing, maintaining, and adjusting components of the J-2 rocket while in space. The scientific team also investigated the design of special maintenance tools and the effectiveness of different pressure suits in performing maintenance work in space.
At the monthly Apollo spacecraft design review meeting with NAA, MSC officials directed NAA to design the spacecraft atmospheric system for 5 psia pure oxygen. From an engineering standpoint, the single-gas atmosphere offered advantages in minimizing weight and leakage, in system simplicity and reliability, and in the extravehicular suit interface. Additional Details: Apollo atmosphere to be pure oxygen.
NAA completed the analysis and design of the Fibreglass heatshield. It duplicated the stiffness of the aluminum heatshield and would be used on all boilerplate spacecraft.
The first completed boilerplate model of the Apollo command module, BP- 25, was subjected to a one-fourth-scale impact test in the Pacific Ocean near the entrance to Los Angeles Harbor. Three additional tests were conducted on August 9.
A NASA program schedule for the Apollo spacecraft command and service modules through calendar year 1965 was established for financial planning purposes and distributed to the NASA Office of Manned Space Flight, Marshall Space Flight Center, and MSC. The key dates were: complete service module drawing release, May 1, 1963; complete command module drawing release, June 15, 1963; manufacture complete on the first spacecraft, February 1, 1964; first manned orbital flight, May 15, 1965. This tentative schedule depended on budget appropriations.
Responsibility for the design and manufacture of the reaction controls for the Apollo command module was shifted from The Marquardt Corporation to the Rocketdyne Division of NAA, with NASA concurrence.
A preliminary NAA report was completed on a literature search concerning fire hazards in 100 percent oxygen and oxygen-enriched atmospheres. This report showed that limited testing would be warranted.
NASA deleted five Apollo mockups, three boilerplate spacecraft, and several ground support equipment items from the NAA contract because of funding limitations.
![]() | Apollo vs N1-L3 - Apollo CSM / LM vs L3 Lunar Complex Credit: © Mark Wade. 11,521 bytes. 621 x 332 pixels. |
Fire broke out in a simulated space cabin at the Air Force School of Aerospace Medicine, Brooks Air Force Base, Tex., on the 13th day of a 14-day experiment to determine the effects of breathing pure oxygen in a long-duration space flight. One of the two Air Force officers was seriously injured. The cause of the fire was not immediately determined. The experiment was part of a NASA program to validate the use of a 5 psia pure oxygen atmosphere for the Gemini and Apollo spacecraft.
Release of the structural design of the Apollo command module was 65 percent complete; 100 percent release was scheduled for January 1 963.
NAA completed the firm-cost proposal for the definitive Apollo program and submitted it to NASA. MSC had reviewed the contract package and negotiated a program plan position with NAA.
The Manned Spacecraft Center (MSC) and the Raytheon Company came to terms on the definitive contract for the Apollo spacecraft guidance computer.
The Aerojet-General Corporation reported completion of successful firings of the prototype service propulsion engine. The restartable engine, with an ablative thrust chamber, reached thrusts up to 21,500 pounds. (Normal thrust rating for the service propulsion engine is 20,500.)
Four Navy officers were injured when an electrical spark ignited a fire in an altitude chamber, near the end of a 14-day experiment at the U.S. Navy Air Crew Equipment Laboratory, Philadelphia, Pa. The men were participating in a NASA experiment to determine the effect on humans of breathing pure oxygen for 14 days at simulated altitudes.
The first static firing of the Apollo tower jettison motor, under development by Thiokol Chemical Corporation, was successfully performed.
North American delivered CM boilerplate (BP) 3, to Northrop Ventura, for installation of an earth-landing system. BP-3 was scheduled to undergo parachute tests at El Centro, Calif., during early 1963.
North American's Rocketdyne Division completed the first test firings of the CM reaction control engines.
North American reported three successful static firings of the launch escape motor. The motor would pull the CM away from the launch vehicle if there were an abort early in a mission.
Two aerodynamic strakes were added to the CM to eliminate the danger of a hypersonic apex-forward trim point on reentry. (During a high-altitude launch escape system (LES) abort, the crew would undergo excessive g forces if the CM were to trim apex forward. During a low-altitude abort, there was the potential problem of the apex cover not clearing the CM. The strakes, located in the yaw plane, had a maximum span of one foot and resulted in significant weight penalties. Additional Details: Two aerodynamic strakes added to Apollo CM.
North American completed construction of Apollo boilerplate (BP) 9, consisting of launch escape tower and CSM. It was delivered to MSC on March 18, where dynamic testing on the vehicle began two days later. On April 8, BP-9 was sent to MSFC for compatibility tests with the Saturn I launch vehicle.
MSC announced the beginning of CM environmental control system tests at the AiResearch Manufacturing Company simulating prelaunch, ascent, orbital, and reentry pressure effects. Earlier in the month, analysis had indicated that the CM interior temperature could be maintained between 294 K (70 degrees F) and 300 K (80 degrees F) during all flight operations, although prelaunch temperatures might rise to a maximum of 302 K (84 degrees F).
North American awarded a $9.5 million letter contract to the Link Division of General Precision, Inc., for the development and installation of two spacecraft simulators, one at MSC and the other at the Launch Operations Center. Except for weightlessness, the trainers would simulate the entire lunar mission, including sound and lighting effects.
At El Centro, Calif., Northrop Ventura conducted the first of a series of qualification tests for the Apollo earth landing system (ELS). The test article, CM boilerplate 3, was dropped from a specially modified Air Force C-133. The test was entirely successful. The ELS's three main parachutes reduced the spacecraft's rate of descent to about 9.1 meters (30 feet) per second at impact, within acceptable limits.
NASA and General Dynamics Convair negotiated a major change on the Little Joe II launch vehicle contract. It provided for two additional launch vehicles which would incorporate the attitude control subsystem (as opposed to the early fixed-fin version). On November 1, MSC announced that the contract amendment was being issued. NASA Headquarters' approval followed a week later.
Most CM subsystem designs frozen.
The Mission Analysis Branch (MAB) of MSC's Flight Operations Division studied the phenomenon of a spacecraft's "skip" when reentering the earth's atmosphere from lunar trajectories and how that skip relates to landing accuracies. Additional Details: Skip lunar reentry trajectories studied for Apollo.
North American officially froze the design of the CM's stabilization and control system.
The first full-scale firing of the SM engine was conducted at the Arnold Engineering Development Center. At the start of the shutdown sequence, the engine thrust chamber valve remained open because of an electrical wiring error in the test facility. Consequently the engine ran at a reduced chamber pressure while the propellant in the fuel line was exhausted. During this shutdown transient, the engine's nozzle extension collapsed as a result of excessive pressure differential across the nozzle skin.
A cluster of two Pioneer tri-conical solid parachutes was tested; both parachutes failed. Because of this unsatisfactory performance, the Pioneer solid-parachute program was officially canceled on July 15.
North American shipped Apollo CM boilerplate 6 and its ground support equipment to WSMR.
The Marquardt Corporation began testing the prototype engine for the SM reaction control system. Preliminary data showed a specific impulse slightly less than 300 seconds.
The Little Joe II qualification test vehicle was shipped from the General Dynamics Convair plant to WSMR, where the test launch was scheduled for August.
North American reported that Lockheed Propulsion Company had successfully completed development testing of the launch escape system pitch control motor.
MSC reported that design of the control and displays panel for the CM was about 90 percent complete. North American was expected to release the design by September 20. Qualification testing of the panels would begin around December 1.
At El Centro, Calif., CM boilerplate (BP) 3, a parachute test vehicle, was destroyed during tests simulating the new BP-6 configuration (without strakes or apex cover). Drogue parachute descent, disconnect, and pilot mortar fire appeared normal. However, one pilot parachute was cut by contact with the vehicle and its main parachute did not deploy. Because of harness damage, the remaining two main parachutes failed while reefed. Investigation of the BP-3 failure resulting in rigging and design changes on BP-6 and BP-19.
The AiResearch Manufacturing Company announced that it had been awarded a $20 million definitive contract for the CM environmental system. (AiResearch had been developing the system under a letter contract since 1961.
The NASA-Industry Apollo Executives Group, composed of top managers in OMSF and executives of the major Apollo contractors, met for the first time. The group met with George E. Mueller, NASA Associate Administrator for Manned Space Flight, for status briefings and problem discussions. In this manner, NASA sought to make executives personally aware of major problems in the program.
Apollo Pad Abort Mission I (PA-1), the first off-the-pad abort test of the launch escape system (LES), was conducted at WSMR. PA-1 used CM boilerplate 6 and an LES for this test.
All sequencing was normal. The tower-jettison motor sent the escape tower into a proper ballistic trajectory. The drogue parachute deployed as programmed, followed by the pilot parachute and main parachutes. The test lasted 165.1 seconds. The postflight investigation disclosed only one significant problem: exhaust impingement that resulted in soot deposits on the CM.
MSC and the U.S. Air Force Aerospace Medical Division completed a joint manned environmental experiment at Brooks Air Force Base, Tex. After spending a week in a sea-level atmospheric environment, the test subjects breathed 100 percent oxygen at 3.5 newtons per square centimeter (5 psi) at a simulated altitude of 8,230 meters (27,000 feet) for 30 days. They then reentered the test capsule for observation in a sea-level environment for the next five days. This experiment demonstrated that men could live in a 100 percent oxygen environment under these conditions with no apparent ill effects.
![]() | Apollo CSM - Apollo CSM with Launch Escape Tower Credit: © Mark Wade. 4,184 bytes. 609 x 174 pixels. |
Three U. S. Air Force test pilots began a five-week training period at the Martin Company leading to their participation in a simulated seven- day lunar landing mission. This was part of Martin's year-long study of crew performance during simulated Apollo missions (under a $771,000 contract from NASA).
The first fuel cell module delivered by Pratt and Whitney Aircraft to North American was started and put on load. The module operated normally and all test objectives were accomplished. Total operating time was four hours six minutes, with one hour at each of four loads-20, 30, 40, and 50 amperes. The fuel cell was shut down without incident and approximately 1,500 cubic centimeters (1.6 quarts) of water were collected.
MSC ordered North American to design the SM's reaction control system with the capability for emergency retrograde from earth orbit.
Boilerplate (BP) 19 was drop tested at El Centro, Calif., simulating flight conditions and recovery of BP-12. A second BP-19 drop, on April 8, removed all constraints on the BP-12 configuration and earth landing system. Another aim, to obtain information on vehicle dynamics, was not accomplished because of the early firing of a backup drogue parachute.
First flight test of Little Joe II using a command module (CM) boilerplate (BP-12) at White Sands Missile Range, N. Mex.
The first prototype of the CM battery for use during reentry was delivered to North American by Eagle-Picher Industries, Inc.
Firings at the Arnold Engineering Development Center (AEDC) and at Aerojet-General Corporation's Sacramento test site completed Phase I development tests of the SM propulsion engine. The last simulated altitude test at AEDC was a sustained burn of 635 seconds, which demonstrated the engine's capability for long-duration firing. Preliminary data indicated that performance was about three percent below specification, but analysis was in progress to see if it could be improved.
Joseph F. Shea, ASPO Manager, in a letter to North American's Apollo Program Manager, summarized MSC's review of the weight status of the Block I and the design changes projected for Block II CSM's.
The Block II design arose from the need to add docking and crew transfer capability to the CM. Reduction of the CM control weight (from 9,500 to 9,100 kilograms (21,000 to 20,000 pounds)) and deficiencies in several major subsystems added to the scope of the redesign. Additional Details: Apollo changes for Block II.
Apollo Saturn Mission A-101, using CM BP-13 atop SA-6 Saturn I launch vehicle, launched at Cape Kennedy, Fla., to prove spacecraft/launch vehicle compatibility. Boilerplate CSM, LM adapter, LES. LES jettison demonstrated.
Apollo systems test. Third orbital test. First closed-loop guidance test.
NAA conducted formal inspection and review of Block II CSM mockup.
Analysis by MSC of the performance of the environmental control system radiators for Block I CM's placed their heat rejection capability at 4,000 Btus per hr, far below the anticipated mission load of 7,220. Additional Details: Block I Apollo CM's heat rejection capability inadequate.
Eagle-Picher Company completed qualification testing on the 25-amperehour reentry batteries for the CM. Shortly thereafter, Eagle-Picher received authorization from North American to proceed with design and development of the larger 40-ampere-hour batteries needed for the later Block I and all Block II spacecraft.
Three Pratt and Whitney fuel cells were operated in a simulated space vacuum at North American for 19, 20, and 21 hours. This was the first time three cells were operated as an electrical power generating subsystem.
MSC and International Business Machines Corporation (IBM) negotiated a $1,500,000 fixed-price contract for the Apollo guidance and navigation system backup computer.
ASPO's Operations Planning Division defined the current Apollo mission programming as envisioned by MSC. The overall Apollo flight program was described in terms of its major phases: Little Joe II flights (unmanned Little Joe II development and launch escape vehicle development); Saturn IB flights (unmanned Saturn IB and Block I CSM development, Block I CSM earth orbital operations, unmanned LEM development, and manned Block II CSM/LEM earth orbital operations); and Saturn V flights (unmanned Saturn V and Block II CSM development, manned Block II CSM/LEM earth orbital operations, and manned lunar missions).
North American conducted the first operational deployment of the launch escape system canards. No problems were encountered with the wiring or the mechanism. Two more operational tests remained to complete the minimum airworthiness test program, a constraint on boilerplate 23.
North American conducted the first drop test of boilerplate 28 at Downey, Calif. The test simulated the worst conditions that were anticipated in a three-parachute descent and water landing. The second drop, it was expected, would likewise simulate a landing on two parachutes. The drop appeared normal, but the spacecraft sank less than four minutes after hitting the water. Additional Details: First drop test of boilerplate 28.
During a mechanical loading test (simulating a 20-g reentry) the CM aft heatshield failed at 120 percent of maximum load. Structures and Mechanics Division engineers inspected the structure. They found that the inner skin had buckled, the damage extending three quarters of the way around the bolt circle that secured the heatshield to the spacecraft's inner structure. Their findings would be used along with data from the recent drop of boilerplate 28 to determine what redesign was necessary.
Joseph G. Thibodaux, Jr., MSC Propulsion and Power Division, reported at an Apollo Engineering and Development technical management meeting that the first J-2 firing of the service propulsion system engine was conducted at White Sands Missile Range (WSMR). Two fuel cell endurance tests of greater than 400 hours were completed at Pratt and Whitney. MSC would receive a single cell for testing during the month.
In its search for some method of reducing water impact pressures, North American was considering adding a 15- to 30.5-cm (6- to 12-in) "lump" to the CM's blunt face. The spacecraft manufacturer was also investigating such consequent factors as additional wind tunnel testing, the effect on heatshield design, and impact upon the overall Apollo program.
North American received NASA's formal go-ahead on manufacture of the Block II spacecraft.
MSC approved plans put forth by North American for mockups of the Block II CSM. For the crew compartment mockup, the company proposed using the metal shell that had originally been planned as a simulator. Except for the transfer tunnel and lighting, it would be complete, including mockups of all crew equipment. Additional Details: Plans for mockups of the Block II Apollo CSM.
A single main parachute was drop-tested at El Centro, Calif., to verify the ultimate strength. The parachute was designed for a disreef load of 11,703 kg (25,800 lbs) and a 1.35 safety factor. The test conditions were to achieve a disreef load of 15,876 kg (35,000 lbs. Preliminary information indicated the parachute deployed normally to the reefed shape (78,017 kg (17,200 lbs) force), disreefed after the programmed three seconds, and achieved an inflated load of 16,193 kg (35,700 lbs), after which the canopy failed. Additional Details: Apollo main parachute drop-tested.
Phase II service propulsion system engine tests at Arnold Engineering Development Center were begun under simulated high altitude conditions with a successful first firing of 30 seconds. A total of nine firings were completed.
North American delivered spacecraft 001's CM to White Sands. The SM was shipped several days later, and would be used for propulsion engine development. Aerojet-General shipped the service propulsion engine to the facility on January 6, 1965.
Ling-Temco-Vought began large-scale developmental testing of the radiator for the Block II CSM environmental control system. One problem immediately apparent was the radiator's performance under extreme conditions.
William A. Lee, chief of ASPO's Operations Planning Division, announced a revised Apollo launch schedule for 1966 and 1967. In 1968, a week-long earth orbital flight would be a dress rehearsal for the lunar mission. "Then the moon," Lee predicted. "We have a fighting chance to make it by 1970," he said, "and also stay within the 20 billion price tag set . . . by former President Kennedy."
North American selected Dalmo-Victor to supply S-band high-gain antennas for Apollo CSM's. (The deployable antenna would be used beyond 14,816 km (8,000 nm) from the earth.) Dalmo-Victor would complete the antenna design and carry out the development work, and North American would procure production units under a supplemental contract.
![]() | Apollo CSM Interior - Interior of the Apollo Command Service Module on display at Kennedy Space Center, Florida. Credit: © Mark Wade. 58,405 bytes. 506 x 392 pixels. |
General Motors' Allison Division completed qualification testing of the propellant tanks for the service propulsion system.
Northrop-Ventura verified the strength of the dual drogue parachutes in a drop test at El Centro, Calif. This was also the first airborne test of the new mortar by which the drogues were deployed and of the new pilot parachute risers, made of steel cables. All planned objectives were met. Additional Details: Apollo dual drogue parachutes in drop test.
Apollo boilerplate 28 underwent its second water impact test. Despite its strengthened aft structure, in this and a subsequent drop on February 9 the vehicle again suffered damage to the aft heatshield and bulkhead, though far less severe than that experienced in its initial test. The impact problem, it was obvious, was not yet solved.
SM 001's service propulsion engine was static-fired for 10 sec at White Sands. The firing was the first in a program to verify the mission profiles for later flight tests of the module. (SM 001 was the first major piece of flight-weight Apollo hardware.)
MSC deleted the requirement for a rendezvous radar in the CSM.
A drop test at EI Centro, Calif., demonstrated the ability of the drogue parachutes to sustain the ultimate disreefed load that would be imposed upon them during reentry. (For the current CM weight, that maximum load would be 7,711 kg (17,000 lbs) per parachute.) Preliminary data indicated that the two drogues had withstood loads of 8,803 and 8,165 kg (19,600 and 18,000 lbs). One of the drogues emerged unscathed; the other suffered only minor damage near the pocket of the reefing cutter.
In a memorandum to ASPO, Samuel C. Phillips, Apollo Program Director, inquired about realigning the schedules of contractors to meet revised delivery and launch timetables for Apollo. Phillips tentatively set forth deliveries of six spacecraft (CSM/LEMs) during 1967 and eight during each succeeding year; he outlined eight manned launches per year also, starting in 1969.
North American proposed an idea for increasing the CM's land landing capability. This could be done, the company asserted, by raising the water impact limits (thus exceeding normal tolerances) and stiffening the shock struts. Additional Details: Increase in the Apollo CM's land landing capability.
North American gave boilerplate 28 its third water drop test. Upon impact, the spacecraft again suffered some structural damage to the heatshield and the core, though much less than it had experienced on its initial drop. Conditions in this test were at least as severe as in previous ones, yet the vehicle remained watertight.
During the flight of boilerplate (BP) 23, the Little Joe II's control system had coupled with the first lateral bending mode of the vehicle. To ensure against any recurrence of this problem on the forthcoming flight of BP-22, MSC asked North American to submit their latest figures on the stiffness of the spacecraft and its escape tower. These data would be used to compute the first bending mode of BP-22 and its launch vehicle.
North American dropped boilerplate 1 twice to measure the maximum pressures the CM would generate during a high-angle water impact. These figures agreed quite well with those obtained from similar tests with a one-tenth scale model of the spacecraft, and supported data from the model on side wall and tunnel pressures.
Part I of the Critical Design Review of the crew compartment and the docking system in the Block II CM was held at North American. Systems Engineering (SED) and Structures and Mechanics (SMD) divisions, respectively, evaluated the two areas. Additional Details: Critical Design Review of the Apollo CM Block II.
North American began a series of water impact tests with boilerplate 1 to obtain pressure data on the upper portions of the CM. Data on the side walls and tunnel agreed fairly well with those obtained from 1/10 scale model drops; this was not the case with pressures on the top deck, however.
Test Series I on spacecraft 001 was completed at WSTF Propulsion Systems Development Facility. Vehicle and facility updating in progress consisted of activating the gimbal subsystem and installing a baffled injector and pneumatic engine propellant valve. The individual test operations were conducted satisfactorily, and data indicated that all subsystems operated normally. Total engine firing time was 765 seconds.
Rocketdyne completed qualification tests on two CM reaction control engines. These were successful. One of the nozzle extensions failed to seat, however, and was rejected. Its failure was being analyzed.
Two CSM fuel cells failed qualification testing, the first failing after 101.75 hrs of the vacuum endurance test. Pratt and Whitney Aircraft determined that the failure was caused by a cleaning fluid which contaminated and plugged the oxygen lines and contaminated the oxygen gas at the electrodes. Additional Details: Two Apollo CSM fuel cells failed qualification testing.
North American conducted the final zero-g trials (part of developmental testing on the CM's waste management system) and reported good results for both urine and feces apparatus.
North American received CM 009 forward and crew compartment heatshields from Avco Corporation. These heatshields were the first CM heatshields received by the contractor with complete ablative application.
Part II of the Critical Design Review of the crew compartment and docking system for the Block II CM was held at Downey, California, using mockups 28 and 27 A. (Part I had been held on March 23-24.) Additional Details: Apollo CM Block II Critical Design Review Part II.
Joseph F. Shea, ASPO Manager, approved Crew Systems Division's recommendation to retain the "shirtsleeve" environment for the CM. The design was simpler and promised greater overall mission reliability; also, it would be more comfortable for the crewmen. Additional Details: Shirtsleeve environment in the Apollo CM.
Structures and Mechanics Division engineers determined that the spacecraft-LEM-adapter would not survive a service propulsion system abort immediately after jettisoning of the launch escape tower. North American planned to strengthen the upper hinges and fasteners and to resize the shock attenuators on spacecraft 009.
Launch escape system (LES) installation for CSM 009 was completed, marking the first LES completion.
Developmental testing began on a new landing device for the CM, one using rockets (mounted on the heatshield) that would be ignited immediately before impact. The current method for ensuring the integrity of the spacecraft during a landing in rough water involved strengthening of the aft structure. The new concept, should it prove practicable, would offer a twofold advantage: first, it would lighten the CM considerably; second, it would provide an improved emergency landing capability.
North American conducted the third in a series of water impact tests on boilerplate 1 to measure pressures on forward portions of the spacecraft. Data from the series supported those from tests with one- tenth scale models of the CM. The manufacturer reported, therefore, that it planned no further full-scale testing.
Marquardt Corporation completed preliminary flight rating tests on the reaction control engine for the SM.
Thiokol Chemical Company completed qualification testing on the tower jettison motor. An ignition delay on February 22 had necessitated a redesign of the igniter cartridge. Subsequently, Thiokol developed a modified pyrogen seal, which the firm tested during late August and early September.
Northrop-Ventura began qualification testing of the earth landing system for Apollo with a drop of boilerplate 19 at El Centro, Calif. The entire landing sequence took place as planned; all parachutes performed well.
MSC directed NAA to make a "predesign" study of a rocket landing system for the Block II CM. (The Center had already studied the system's feasibility and had conducted full-scale drop tests.)
Independent studies were made at MSC and North American to determine effects and impact of off-loading certain Block II service propulsion system components for Saturn IB missions. The contractor was requested to determine the weight change involved and schedule and cost impact of removing one oxidizer tank, one fuel tank, one helium tank and all associated hardware (fuel and oxidizer transfer lines, propellant quantity sensors and certain gaging wire harnesses) from CSM 101 and CSM 103. The MSC study was oriented toward determining technical problems associated with such a change and the effects on spacecraft operational requirements. The North American study indicated that removing the equipment would save about 690 000, along with a weight reduction of approximately 454 kg (1,000 lbs). Additional Details: Reduced Apollo Block II service propulsion system for Saturn IB missions.
![]() | Apollo with Vanes Credit: NASA. 47,826 bytes. 472 x 330 pixels. |
North American reported two service propulsion engine failures at AEDC and a third at WSMR. At the first location, both failures were attributed to separation of the thrust chamber from the injector assembly; in the latter instance, weld deficiencies were the culprit. Analysis of all these failures was continuing.
NASA launched Apollo mission PA-2, a test of the launch escape system (LES) simulating a pad abort at WSMR. All test objectives were met. The escape rocket lifted the spacecraft (boilerplate 23A) more than 1,524 m (5,000 ft) above the pad. The earth landing system functioned normally, lowering the vehicle back to earth. This flight was similar to the first pad abort test on November 7, 1963, except for the addition of canards to the LES (to orient the spacecraft blunt end forward after engine burnout) and a boost protective cover on the CM. PA-2 was the fifth of six scheduled flights to prove out the LES.
An RCS oxidizer tank failed during a test to demonstrate propellant compatibility with titanium tanks. This was the first of seven tanks to fail from a group of ten tanks put into test to investigate a failure that occurred during February 1965. These results caused an intensive investigation to be undertaken.
North American began redesigning the side hatch mechanism in the CM to satisfy the requirement for extravehicular transfer from Block II spacecraft. Two basic modifications to the Block I mechanism were required: (1) enlarging it to overcome thermal warpage; and (2) adding some hinge retention device to secure the hatch once it was opened.
North American recommended to MSC that, for the time being, the present method for landing the CM (i.e., a passive water landing) be maintained. However, on the basis of a recent feasibility study, the contractor urged that a rocket landing system be developed for possible use later on. North American said that such a system would improve mission reliability through the increase in impact capability on both land and water.
NASA Headquarters authorized North American to subcontract the Block II CSM fuel cells to Pratt and Whitney. Estimates placed the cost at $30 million.
At North American's drop facility, a malfunction in the release mechanism caused boilerplate 1 to impact on land rather than water. After a recurrence of this accident on August 6, a team of investigators began looking into the problem. Drops were suspended pending their findings. These incidents aggravated delays in the test program, which already was seven weeks behind schedule.
NASA's office at Downey, Calif., approved the contract with the Marquardt Corporation for the procurement of Block II SM reaction control system engines. Estimated cost of the fixed price contract would be $6.5 million. Marquardt was supplying the Block I SM engines.
During tests of the Apollo earth landing system (ELS) at El Centro, Calif., boilerplate (BP) 6A sustained considerable damage in a drop that was to have demonstrated ELS performance during a simulated apex-forward pad abort. Oscillating severely at the time the auxiliary brake parachute was opened, the spacecraft severed two of the electrical lines that were to have released that device. Although the ELS sequence took place as planned, the still-attached brake prevented proper operation of the drogues and full inflation of the mains. As a result, BP-6A landed at a speed of about 50 fps.
Samuel C. Phillips, Apollo Program Director, listed the six key checkpoints in the development of Apollo hardware:
North American conducted another in their series of impact tests with boilerplate 28. This drop tested the toroidal section of the spacecraft (heatshield and equipment bay structure) in impact at high angle and maximum horizontal velocity. The spacecraft suffered no visible damage. Some water leaked into the vehicle, but this was blamed on the boilerplate structure itself and the apex-down attitude after impact.
At a Customer Acceptance Readiness Review at North American, NASA formally accepted spacecraft 002. The vehicle was then demated and shipped to White Sands.
A drop in the boilerplate 6A series, using flight-qualifiable earth landing system (ELS) components, failed because the braking parachute (not a part of the ELS) did not adequately stabilize the vehicle. MSC invited North American and Northrop-Ventura to Houston to explain the failure and to recommend corrective measures.
On August 26, the attachments for the pilot parachute mortar had failed during static testing on CM 006. The fittings had been redesigned and the test was not repeated. This test, the final one in the limit load series for the earth landing system, certified the structural interface between the CM and the earth landing system for the 009 flight.
Apollo spacecraft 009, first of the type that would carry three astronauts to the moon and back, was accepted by NASA during informal ceremonies at North American. Spacecraft 009 included a CM, SM, launch escape system, and adapter. It went to Cape Canaveral for integration with the first Saturn IB (Saturn IB and SIVB stages received August 1965). The spacecraft was stacked on the launch vehicle on 26 December.
Samuel C. Phillips, Apollo Program Director, notified the Center directors and Apollo program managers in Houston, Huntsville, and Cape Kennedy that OMSF's launch schedule for Apollo-Saturn IB flights had been revised, based on delivery of CSMs 009 and 011:
The Block I service propulsion system engine successfully completed the first altitude qualification tests at AEDC.
North American informed MSC of a fire in the reaction control system (RCS) test cell during a CM RCS test for spacecraft 009. The fire was suspected to have been caused by overheating the test cell when the 10 engines were activated, approximately 30 sec prior to test completion. An estimated test delay of two to three weeks, due to shutdown of the test cell for refurbishment, was forecast. MSC informed the Apollo Program Director that an investigation was underway.
Apollo Mission Simulator No. 1 was shipped from Link Group, General Precision, Binghamton, New York, to MSC.
From September 1962 NASA planned to fly four early manned Apollo spacecraft on Saturn I boosters. A key prerequisite for these flights was complete wringing out of the launch escape system. Additional Details: Apollo SA-11.
The Block II CSM Critical Design Review (CDR) was held at North American, Downey, Calif. The specifications and drawings were reviewed and the CSM mockup inspected. Review Item Dispositions were written against the design where it failed to meet the requirements.
As a result of the CDR North American would update the configuration of mockup 27A for use in zero-g flights at Wright-Patterson AFB. The flights could not be rescheduled until MSC approved the refurbished mockup as being representative of the spacecraft configuration.
Nine review item dispositions were submitted at the Block II critical design review concerning the earth landing system and shock attenuation system (struts). Six were on specifications, one on installation drawings, and two on capability. The two most significant were:
At-sea operational qualification tests, using boilerplate 29 to simulate spacecraft 009, were completed. All mechanical system components performed satisfactorily, except for the recovery flashing light. Additional Details: Apollo at-sea operational qualification tests completed.
CSM ultimate static testing began. A failure occurred at 140 percent of the limit load test which simulated the end of the first-stage Saturn V boost. Additional Details: Apollo CSM ultimate static testing began.
The SM reaction control system engine qualification was completed with no apparent failures.
The first fuel cell system test at White Sands Test Facility was conducted successfully. Primary objectives were: 1 to verify the capability of the ground support equipment and operational checkout procedure to start up, operate, and shut down a single fuel cell power plant; and 2 to evaluate fuel cell operations during cold gimbaling of the service propulsion engine.
A decision made at a Program Management Review eliminated the requirement for a land impact program for the CM to support Block I flights. Post-abort CM land impact for Saturn IB launches had been eliminated from Complex 37 by changes to the sequence timers in the launch escape system abort mode. The Certification Test Specification and related Certification Test Requirements would reflect the new Block II land impact requirements.
Apollo Mission A-004 was successfully accomplished at White Sands Missile Range. This was the first flight test utilizing the Apollo Block I type spacecraft and the sixth and final test of the Apollo CSM development program at WSMR. Additional Details: Little Joe II A-004.
![]() | Convair Apollo Credit: NASA. 38,525 bytes. 500 x 364 pixels. |
Apollo-Saturn 201 was launched from Cape Kennedy, with liftoff of an Apollo Block I spacecraft (CSM 009) on a Saturn IB launch vehicle at 11:12:01 EST. Launched from Launch Complex 34, the unmanned suborbital mission was the first flight test of the Saturn IB and an Apollo spacecraft. Total launch weight was 22,000 kilograms.
Spacecraft communications blackout lasted 1 minute 22 seconds. Reentry was initiated with a space-fixed velocity of 29,000 kilometers per hour. CM structure and heatshields performed adequately. The CM was recovered by the USS Boxer from the Atlantic about 72 kilometers uprange from the planned landing point. (8.18 S x 11.15 W).
NASA originally planned to fly four early manned Apollo spacecraft on Saturn I boosters. The decision was made to conduct all Apollo CSM tests on the more powerful Saturn IB booster. These flights were cancelled in October 1963, before crews were selected. This series of four partial-system lightweight Apollos would have run from fall 1965 to the end of 1966, concurrent with the Gemini program.
Associate Administrator for Manned Space Flight George E. Mueller acknowledged receipt from Joseph F. Shea, the Apollo Spacecraft Program Manager at MSC, of a detailed technical description of MSC's plans and development progress toward developing a landing rocket system for Apollo. (MSC had undertaken this effort some months earlier at Mueller's specific request.) Mueller advised Shea that he had asked AAP Deputy Director John H. Disher to work closely with Shea's people to devise a land landing system for AAP built on Houston's effort for Apollo.
Apollo Program Director Samuel C. Phillips notified the three manned space flight Centers that they were requested to plan for a dual AS-207/208 mission, assuming that launch would occur one month later than the 207 launch now scheduled.
The first integrated test of the service propulsion system, electrical power system, and cryogenic gas storage system was successfully conducted at the White Sands Test Facility.
Spacecraft 007 and 011 were delivered to NASA by North American Aviation. Spacecraft 007 was delivered to Houston to be used for water impact and flotation tests in the Gulf of Mexico and in an environmental tank at Ellington AFB. It contained all recovery systems required during actual flight and the total configuration was that of a flight CM.
The CM of spacecraft 011 was similar to those in which astronauts would ride in later flights and the SM contained support systems including environmental control and fuel cell systems and the main service propulsion system. Spacecraft 011 was scheduled to be launched during the third quarter of 1966.
NASA originally planned to fly four early manned Apollo spacecraft on Saturn I boosters. The decision was made to conduct all Apollo CSM tests on the more powerful Saturn IB booster. These flights were cancelled in October 1963, before crews were selected. This series of four partial-system lightweight Apollos would have run from fall 1965 to the end of 1966, concurrent with the Gemini program.
The unmanned suborbital Apollo-Saturn 202 mission was successfully flown - the third Saturn IB flight test and the second CM heatshield flight test. The 202 included an uprated Saturn I (Saturn IB) launch vehicle (S-IB stage, S-IVB stage, and instrument unit) and the Apollo 011 spacecraft (spacecraft-lunar module adapter, service module, command module, and launch escape system). Liftoff was from Launch Complex 34 at Cape Kennedy at 1:15 p.m. EDT. The command module landed safely in the southwest Pacific Ocean, near Wake Island 1 hour 33 minutes after liftoff. It was recovered by the U.S.S. Hornet about 370 kilometers uprange from the recovery ship (16.07 N 168.54 E). Additional Details: Apollo 202.
NASA originally planned to fly four early manned Apollo spacecraft on Saturn I boosters. The decision was made to conduct all Apollo CSM tests on the more powerful Saturn IB booster. These flights were cancelled in October 1963, before crews were selected. This series of four partial-system lightweight Apollos would have run from fall 1965 to the end of 1966, concurrent with the Gemini program.
In a memorandum to the NASA Deputy Administrator, Associate Administrator for Manned Space Flight George E. Mueller commented on the AS-202 impact error. Mueller said the trajectory of the August 25 AS-202 mission was essentially as planned except that the command module touched down about 370 kilometers short of the planned impact point. Additional Details: Apollo AS-202 impact error analzyed.
Apollo Program Director Samuel C. Phillips told Mark E. Bradley, Vice President and Assistant to the President of The Garrett Corp., that "the environment control unit, developed and produced by Garrett's AiResearch Division under subcontract to North American Aviation for the Apollo spacecraft was again in serious trouble and threatened a major delay in the first flight of Apollo." Additional Details: Apollo environment control unit in serious trouble.
The first manned flight of the Apollo CSM, the Apollo C category mission, was planned for the last quarter of 1966. Numerous problems with the Apollo Block I spacecraft resulted in a flight delay to February 1967. The crew of Virgil I. Grissom, Edward H. White II, and Roger B. Chaffee, was killed in a fire while testing their capsule on the pad on 27 January 1967, still weeks away from launch. The designation AS-204 was used by NASA for the flight at the time; the designation Apollo 1 was applied retroactively at the request of Grissom's widow. Additional Details: Apollo 204.
A TWX from NASA Headquarters to MSC, MSFC, and KSC ordered checkout and launch preparation of AS-501 to proceed as planned, except that the CM would not be pressurized in an oxygen environment pending further direction. If AS-501 support, facility, or work force should conflict with the activities of the AS-204 Review Board, the Board would be given priority.
It was originally planned to make a second solo flight test of the Block I Apollo CSM on a Saturn IB. This flight was referred to by everyone outside of the astronaut office as AS-205 or CSM-014. This flight was finally seen as unnecessary; the decision to cancel it came on November 16 and was officially announced on December 22, 1966; the Schirra crew instead became, briefly, the backup crew to Apollo 1 (replacing the original backup crew of McDivitt, Scott, Schweickart). After the Apollo 1 fire on January 27, 1967, the Schirra crew was assigned to Apollo 7, the first manned flight test of the new Block II Apollo CSM-101.
MSC notified NASA Hq. that - with the changes defined for the Block II spacecraft following the January 27 Apollo 204 fire and with CSM delivery schedules now reestablished - it was necessary to complete a contract for three additional CSMs requested in 1966. North American Aviation had responded September 15, 1966, to MSC's February 28 request for a proposal, but action on a contract had been suspended because of the AS-204 accident. NASA Hq. on June 27, 1967, authorized MSC to proceed.
Robert O. Aller, NASA OMSF, told Apollo Program Director Samuel C. Phillips that considerable analysis, planning, and discussion had taken place at MSC on the most effective sequence of Apollo missions following the first manned flight (Apollo 7). The current official assignments included three CSM/LM missions for CSM/LM operations, lunar simulation, and lunar capability. MSC's Flight Operations Directorate (FOD) had offered an alternate approach of that sequence by proposing that the third mission be a lunar-orbit mission rather than a high earth-orbit mission. Aller preferred the FOD proposal, since it would offer considerable operational advantages by conducting a lunar-orbital flight before the lunar landing. He recommended Phillips consider that sequence of missions and that consideration be given to including it as a prime or alternate mission in the Mission Assignments Document. "Identifying it in that document," Aller said, "would initiate the necessary detailed planning."
Before the Apollo 1 fire, it was planned that McDivitt's crew would conduct the Apollo D mission - a first manned test in earth orbit of the Lunar Module. Separate Saturn IB launches would put Apollo Block II CSM 101 / AS-207 and Lunar Module LM-2 / AS-208 into earth orbit. The crew would then rendezvous and dock with the lunar module and put it through its paces. After the fire, it was decided to launch the mission on a single Saturn V as Apollo 9. CSM-101 instead would be used to accomplish the Apollo C mission that Grissom's crew was to have flown.
When Schirra's Apollo 2 / AS-205 mission was cancelled in November 1966, the booster went to McDivitt's mission, and it was called AS (or Apollo) 205/208, or AS-258 (before Schirra's cancellation, McDivitt's was AS-278, because it used Saturn IB boosters 207 and 208).
During operational checkout procedures on CSM 017, which included running the erasable memory program before running the low-altitude aborts, the guidance and navigation computer accidentally received a liftoff signal and locked up. Investigation was initiated to determine the reason for the liftoff signal and the computer lockup (switch to internal control). No damage was suspected.
The merger of North American Aviation, Inc., and Rockwell-Standard Corp. became effective and was announced. The company was organized into two major groups, the Commercial Products Group and the Aerospace and Systems Group. The new company would be known as North American Rockwell and use the acronym NR.
In spite of efforts to eliminate all flammable materials from the interior of the spacecraft cabin during flight, it was apparent that this could not be completely accomplished. For example, silicone rubber hoses, flight logs, food, tissues, and other materials would be exposed with in the cabin during portions of the mission. However, flammable materials would be outside their containers only when actually needed. Special fire extinguishers would be carried during flight.
A proposal to use a Ballute system rather than drogue parachutes to deploy the main chutes on the Apollo spacecraft was rejected. It was conceded that the Ballute system would slightly reduce dynamic pressure and command module oscillations at main parachute deployment. However, these advantages would be offset by the development risks of incorporating a new and untried system into the Apollo spacecraft at such a late date.
![]() | Apollo Competitors Credit: NASA. 36,351 bytes. 611 x 419 pixels. |
NASA Hq. informed MSC that NASA Deputy Administrator Robert C. Seamans, Jr., had approved the project approval document authorizing four additional CSMs beyond No. 115A. MSC was requested to proceed with all necessary procurement actions required to maintain production capability in support of projected schedules for these items.
A parachute test (Apollo Drop Test 84-1) failed at EI Centro, Calif. The parachute test vehicle (PTV) was dropped from a C-133A aircraft at an altitude of 9,144 meters to test a new 5-meter drogue chute and to investigate late deployment of one of the three main chutes. Additional Details: Apollo Drop Test failure 84-1.
Apollo 4 (AS-501) was launched in the first all-up test of the Saturn V launch vehicle and also in a test of the CM heatshield. The Saturn V, used for the first time, carried a lunar module test article (LTA-10R) and a Block I command and service module (CSM 017) into orbit from KSC Launch Complex 39, Pad A, lifting off at 7:00:01 a.m. EST - one second later than planned. The launch was also the first use of Complex 39. The spacecraft landed 8 hours 37 minutes later in the primary recovery area in the Pacific Ocean, near Hawaii, about 14 kilometers from the planned point (30.06 N 172.32 W). CM, apex heatshield, and one main parachute were recovered by the carrier U.S.S. Bennington
Main objectives of the mission were to demonstrate the structural and thermal integrity of the space vehicle and to verify adequacy of the Block II heatshield design for entry at lunar return conditions. These objectives were accomplished.
The S-IC stage cutoff occurred 2 minutes 30 seconds into the flight at an altitude of about 63 kilometers. The S-II stage ignition occurred at 2 minutes 32 seconds and the burn lasted 6 minutes 7 seconds, followed by the S-IVB stage ignition and burn of 2 minutes 25 seconds. This series of launch vehicle operations placed the S-IVB and spacecraft combination in an earth parking orbit with an apogee of about 187 kilometers and a perigee of 182 kilometers. After two orbits, which required about three hours, the S-IVB stage was reignited to place the spacecraft in a simulated lunar trajectory. This burn lasted five minutes. Some 10 minutes after completion of the S-IVB burn, the spacecraft and S-IVB stage were separated, and less than 2 minutes later the service propulsion subsystem was fired to raise the apogee. The spacecraft was placed in an attitude with the thickest side of the CM heatshield away from the solar vector. During this four-and-one-half-hour cold-soak period, the spacecraft coasted to its highest apogee - 18,256.3 kilometers. A 70 mm still camera photographed the earth's surface every 10.6 seconds, taking 715 good-quality, high-resolution pictures.
About 8 hours 11 minutes after liftoff the service propulsion system was again ignited to increase the spacecraft inertial velocity and to simulate entry from a translunar mission. This burn lasted four and one half minutes. The planned entry velocity was 10.61 kilometers per second, while the actual velocity achieved was 10.70.
Recovery time of 2 hours 28 minutes was longer than anticipated, with the cause listed as sea conditions - 2.4-meter swells.
The third Apollo flight announced on December 22, 1966, was the Apollo E mission - a test of the Apollo lunar module in high earth orbit. The Borman crew would be launched aboard a Saturn V, and put into a very high earth orbit. In mid-1968 Collins had to leave the crew due to a medical problem, and was replaced by Lovell. By late 1968, Apollo 7 had flown the Apollo C mission, but delays with the lunar module meant that neither the D or E profile missions could be flown. In order to beat the Russians around the moon, it was decided that the E mission would be cancelled and instead Borman's crew would fly an Apollo CSM into lunar orbit. This became Apollo 8.
An Apollo drop test failed at El Centro, Calif. The two-drogue verification test had been planned to provide confidence in the drogue chute design (using a weighted bomb) before repeating the parachute test vehicle (PTV) test. Preliminary information indicated that in the test one drogue entangled with the other during deployment and that only one drogue inflated. The failure appeared to be related to a test deployment method rather than to drogue design. The test vehicle was successfully recovered by a USAF recovery parachute-intact and reusable.
A Parachute Test Vehicle (PTV) test failed at El Centro, Calif. The PTV was released from a B-52 aircraft at 15,240 meters and the drogue chute programmer was actuated by a static line connected to the aircraft. One drogue chute appeared to fail upon deployment, followed by failure of the second drogue seven seconds later. Additional Details: Apollo Parachute Test Vehicle failed.
Apollo drogue chute test 99-5 failed at the El Centro, Calif., parachute facility. The drop was conducted to